Kitchen remodel for Jordan Reyes
Send to client writes a message to the Demo Outbox on this server. It does not send email.
The problem
The existing kitchen no longer supports how the household cooks, stores, and gathers. Worn surfaces, a dated layout, and tired fixtures slow every meal and make the room feel smaller than it is.
The solution
Copperline Kitchen & Bath Co. delivers a scoped renovation with site measure, licensed trades, and one point of contact from demolition through walkthrough. Cabinets, surfaces, and services are sequenced so the household can plan around a clear calendar instead of an open-ended job.
Scope
Budget range: $15,000 to $30,000 · Kickoff Nov 16, 2026
- Cabinets
- Countertops
- Lighting
- Design consultation
Timeline
Phase 1
Design & Measure
Nov 16, 2026 to Nov 20, 2026
5 business days
On-site measure, existing-condition photos, and finish confirmation for the kitchen. Drawings and a written schedule go to the client before demolition.
Phase 2
Demolition & Prep
Nov 23, 2026 to Dec 2, 2026
8 business days
Protect adjacent rooms, remove designated finishes, and prepare substrate, plumbing, and electrical rough-in for the kitchen.
Phase 3
Install & Finish
Dec 3, 2026 to Dec 24, 2026
16 business days
Set cabinets or vanities, counters, tile, fixtures, lighting, and flooring in the published sequence, then punch remaining items.
Phase 4
Walkthrough & Handoff
Dec 29, 2026 to Dec 30, 2026
2 business days
Client walkthrough, care notes, and close-out of remaining items. Final balance is due on completion.
Investment
| Item | Code | Amount (CAD) |
|---|---|---|
| Kitchen cabinetry package: made-to-measure boxes, doors, and hardware | KIT-CAB | CA$18,500.00 |
| Kitchen countertops: quartz slab supply and finish | KIT-CNT | CA$7,200.00 |
| Kitchen lighting: ceiling, under-cabinet, and control | KIT-LGT | CA$1,800.00 |
| Kitchen design consultation: measure, drawings, and schedule | KIT-DSN | CA$1,500.00 |
| Total | CA$29,000.00 | |
| 50% deposit, due at signing | CA$14,500.00 | |
| 50% balance, due on completion | CA$14,500.00 | |
Prices shown before applicable taxes
Terms
- Figures are in Canadian dollars and are valid until Oct 31, 2026.
- Prices shown before applicable taxes. Applicable taxes are determined at signing.
- A 50% deposit (CA$14,500.00) is due at signing. The remaining CA$14,500.00 is due on completion.
- Deposit refundable until 5 business days before scheduled kickoff, minus documented out-of-pocket costs; non-refundable once the first kickoff meeting happens.
- Refund deadline for this proposal: Nov 9, 2026 (five business days before kickoff on Nov 16, 2026).
- Timelines count business days only (Monday to Friday, excluding Ontario public holidays) and assume site access plus timely selections.
- Changes to scope after signing are priced as written change orders before the extra work starts.
Signature
Awaiting send. Use Send to client, then the signer can draw on the pad.
Jordan Reyes